JJ White crews are expanding the production capacity for polypropylene plastic resins at a major Mid-Atlantic Refinery
- Over 300,000 feet of power/communication cable to install:
- Power
- Communication
- Instrumentation
- 886 power terminations
- 7044 instrumentation terms
- 6383 lighting related terminations
- Over 63,000 feet heat tracing
- Major milestones completed are: (tested and operational)
- (T-2) Telephone communication system.
- Lightning protection system
- New Boiler house (work fronts added)
- Fiber terminations for DCS & SIS system
- Ground level 126’ elevation (T-2) ITP released to LYB. (punch list items remaining)
- Isolated/equipment grounding
- Over 38,000 feet cable tray
- Over 11,000 feet instrument tubing
- Over 20,000 feet Conduit