Details
- 4 man Crew: 1 – SF GF / 2 – SFW / 1 – SF
- Original Scope was to replace all piping from the block valves at the pumps up to the 2nd floor making the final tie in at the existing 24” elbow
- Original Work Schedule was 6 weeks with a 6 x 10 schedule. The client requested us to modify the work scope to 5 weeks on a 5 x 10 schedule
- All work was completed on time according to the client’s new schedule without any incidents.
- Original Planned Man Hours: 1935
- Project Completion Man Hours: 1010
Challenges & Barriers
- Low head room to hang proper rigging. Brand Scaffolding was able to build scaffolding rated for rigging to assist with varies points to hang chain blocks.
- Removing old piping from the basement and 1st floor using the Gantry Crane to lift through the designated shaft to the outside hard deck.
- Lowering new piping from the outside hard deck into the basement and 1st floor using the Gantry Crane.
- All was done successfully without incident.
Work Completed
- Demo all old piping and valves along with disposal.
- Fabricated all new piping on site and install.
- Welds:
- 14 – 24” welds
- 10 – 16” welds
- 1 – 12” weld
- 6 – 4” welds
- 5 – 6” welds
- Several miscellaneous small bore welds 2” and under
- Valves:
- 1 – 16” 150# Check Valve
- 1 – 16” 150# Gate Valve
- 1 – 24” 150# Gate Valve
- 1 – 6” 150# Gate Valve
- 1 – 4” 150# Gate Valve